2021 Street & Utility Project

The 2021 Street and Utility Project includes Areas A and B. Each area is broken into phases. View this subpage for current status updates. Project Areas A and B

Area A: Phases 1, 2, & 3   

Phase 1 2 3 Map  210903Phase 1 Current Status: All storm sewer and curbing complete. All streets paved. Second layer of pavement on Sherburne Avenue and Euclid Avenue to be placed after mailboxes and boulevard restoration completed.

Phase 2 & 3 Current Status: Reclaiming pavement surface and temporary mailbox removal week of September 6th. Storm sewer pipe an inlet structures to be installed on Rd Oak Dive, Westwood and Shady Lane the following week. Gravel grading to begin shortly there after. Concrete curbing likely in several weeks and paving in mid October. Curbing and paving work will be scheduled on opposite phased streets to allow residents to park close. The streets are very narrow and do not allow room for contractor and vehicles to be on the street at same time. Hand delivered notices will take place to coordinate. 

Area B: Phases 4 & 5  

Phase 4 5 Map  210903

Phase 4 Current Status: (Will Street Powell Circle North & Powell St (north of Powell Circle East) Reclaiming pavement surface and temporary mailbox removal to take place week of September 13. Storm sewer pipe and inlet structures to be installed end of September. Curbing and sidewalk anticipated to be installed early October. Paving and restoration later part of October and early November. Mailboxes will be reinstalled late October. Phase 4 to be delivered week of September 6. Hand delivered notices will take place to coordinate. 

Phase 5 Current Status: (Powell Circle East, Powell Circle West and Powell Street (south of Powell Circle East) Storm sewer structure and watermain gate valve component availability is causing scheduling problems.